The British SSN (nuclear attack sub) Triumph just completed its mid-career refueling and refurbishment. This is the last of the Trafalgar-class boats to go through this process, which took nearly five years and 2.75 million man hours. There were some 30,000 tasks on the to-do list, and 75,000 items on the boat were repaired, replaced or otherwise meddled with. As a crew was reassembled, they spent thousands of hours on control room and equipment simulators, preparing to take the refurbished boat out for three months of trials, to make sure everything still works. The Triumph will then be able to serve for another twelve years.
|